top of page
N I N E E L M S
P R O J E C T
C L I E N T
C O N S U L T A N T
A D D R E S S
P E R I O D
V A L U E
Nine Elms
Vital Energi
Calford Seadon
Nine Elms
12 Months
£1,500,000
T4 M&E Ltd were contracted to install the District Heating and Pipework infrastructure at Nine Elms Point, a 647 home development sitting above the Sainsburys flagship superstore. The installation consisted of two thermal stores with a combined capacity of 60,000 litres. In addition, the separate chiller plant room includes four 460kW water cooled chillers with a combined capacity of 1890kW and three roof-level 850kW dry air coolers and a 5000L thermal store.
1/19
bottom of page